The university president inspects the infrastructure project for the second part of the university

The President of the University 01.06.2023 27328

                    Today, Thursday, June 1, 2023, Professor Dr. El-Sayed Mohamad Dadour, President of the University, inspected the infrastructure project for about 100 acres inside the university campus, where he received a report from specialists on the size of the invisible achievements that took place in that area and finished 100%, allowing the construction of any building from the projects. The new building is anywhere, and only the link remains with the building that will be completed. It is worth noting that the part that the university president inspected today is a mirror of half of the university whose construction was completed in previous years, and thus 100% of the infrastructure of the new part has been equipped as follows:

Firstly, drinking water, and 100% of its infrastructure has been completed, with a total of eight kilometers of plastic pipes of different diameters, eighteen cockpits for the main network, and five cockpits for the sub-water network.

Secondly, the irrigation system for green areas, and 100% of its infrastructure has been completed, with a total of seventeen kilometers of pipes of different specifications and diameters, and nine cockpits for the irrigation system.

Third, the fire system, and 100% of its infrastructure has been completed, with a total of eleven kilometers of pipes of different diameters, and nine cockpits for the fire system.

Fourth, the sewage system, and 100% of its infrastructure has been completed, with a total of thirteen kilometers of pipes of different diameters, and five hundred trays for collecting waste water.

Fifthly, the electrical works, and 100% of its infrastructure has been completed, with a total of one distributor room, six rooms for generators, and thirteen rooms for transformers. The remaining works are the connections to the buildings after their construction.

Sixth: Road works: 100% of the chopping works have been completed, with a total area of ??ten thousand kilometers of different widths, which are eight roads.

This area, which was visited by the president of the university and designated for future construction projects, is considered to facilitate the mission of future university leaders when starting new projects. and the University Council has approved in previous sessions these future projects included in the general plan of the total university campus project. It includes, among other things, the buildings of the faculties of applied arts and agriculture, the laboratories and workshops of the practical faculties, the laboratories complex of the faculties of the medical sectors, and the electronic examination complex for the second stage, amphitheaters and halls for the need for the educational process similar to the previous stage, a center for student services, a conference hall, the university’s permanent printing press, university stores, and other projects that will be adopted by the new university leadership in the future, especially after completing those operations related to the infrastructure of the new projects area..